Consolidating 3 Offices Into One New Headquarters
CE+T America, Duluth, GA
When CE+T America decided to bring its two Suwanee, GA locations and its Austin, TX office together under one roof in Duluth, GA, we took on the technology side of the move, from the first walk-through of the empty building to the final adjustments on-site.
At a Glance
The project in numbers
3 offices into 1
About 40 users from two Suwanee, GA locations and an Austin, TX office brought together in one new Duluth, GA headquarters
15 WiFi 6 access points
Coverage designed for both the office and the warehouse, backed by 8 managed PoE switches
About 5,000 ft of Cat6
New cabling run, terminated, labeled, and tested across the office, warehouse, and exterior
The Challenge
Three offices, two states, one new building
CE+T America is the US arm of a global power conversion group. Combining three offices and about 40 users meant far more than moving desks, especially with people moving in phases rather than all at once. The new building had office, warehouse, lab, and production space that all needed reliable connectivity, and it had to tie back to the parent company's network in Belgium. All of it had to be planned around construction, carrier lead times, and a business that still had to keep running.
The Solution
One partner for the whole technology move
We led the project from design through installation, coordinating the carrier, equipment vendors, on-site cabling crews, the building's contractors, and the client's IT team overseas, so the client had one point of contact throughout.
Planned before the walls were ready
We surveyed the empty building, mapped the data closets against the floor plan, designed the network, and handled quoting, ordering, and vendor coordination.
Lined up internet early
We started the business fiber order months ahead, then worked with the carrier through site requirements and installation at the new address.
Built the new network
A next-generation firewall, managed PoE switching, fiber uplinks, rack power, and UPS protection went in as one standardized design.
Cabled a working warehouse
Using scissor lifts and custom-fabricated mounts, the crew ran new pathways and cabling, then installed access points and cameras indoors and out.
Connected to the global parent company
We coordinated with the CE+T IT team in Belgium on the network design and a secure site-to-site VPN, so the new headquarters connected to the wider organization.
Closed down the old sites
We removed access points, cameras, and network infrastructure from the old space, inventoried the equipment, and delivered it to Duluth.
The Timeline
How the project came together
October 2023
Estimate approved, internet ordering started, and the on-site survey completed.
Late 2023 to early 2024
Network design finalized, hardware ordered, and the project coordinated with vendors.
March 2024
Internet installation, new cabling, access points, cameras, and network equipment installed on-site.
The following months
Users moved in phases: the two Suwanee offices first, then the Austin office over roughly the next six months. Access points and cameras were adjusted as racks went up and the warehouse was renovated, and the site was prepared for its occupancy inspection.
The Results
A single headquarters, built to last
- 01 One headquarters and one standardized network in place of three separate offices
- 02 Wireless and camera coverage across the office and warehouse
- 03 Secure connectivity between Duluth and the global parent company
- 04 A long-term partnership: CE+T America remains a CITG Tech managed IT client today
“Great support! Very professional with competent technicians. Highly recommended.”
Related Services
Services used on this project
Get Started
Planning an office move?
Tell us about your timeline and locations, and we'll map out the technology side of the move.